Progress

The REFHYNE 2 project commenced in October 2021 and will run until 2029.

Design, Permitting and Engineering

Q4 2021

REFHYNE 2 project start

Construction and Commissioning

Q3 2024

FID reached

Q4 2024

FID reached

Q2 2025

Project partner site visit

Operation and Dissemination

2027

Electrolyser operational

2029

Final reports published

Construction

Construction began on the REFHYNE 2 project at the end of 2024, at the Shell Energy and Chemicals Park Rheinland, with close collaboration from project partners Linde and ITM. The hydrogen produced by the 100 MW electrolyser will be used within the refinery itself in existing refinery operations.

In parallel with the detailed technical work to implement the electrolyser, an experienced research and dissemination team will lead a campaign to validate the electrolyser performance in the field, extract technical lessons learnt and then develop techno-economic analysis which underpins clear conclusions on the environmental, societal, and policy implications of rapid electrolyser scale up.

This will be disseminated throughout the project, to increase confidence in and acceptance of hydrogen technologies.  Stay up to date with the REFHYNE 2 project reports by exploring the Resources page.

News

Final Investment Decision taken by Shell for REFHYNE 2

Final Investment Decision taken by Shell for REFHYNE 2

Shell has taken a final investment decision on REFHYNE 2, a 100-megawatt renewable proton-exchange membrane (PEM) hydrogen electrolyser at the Shell.

Read more...